Willow Lane, Mitcham
Submitted by admin on April 4, 2006 - 13:25.
10% renewables | case_studies | energy | merton | planning | renewable
The project consisted of the installation of a solar PV system onto the profiled steel sheet roof of a new business park development in Mitcham, South London, and electrical connection into the existing system.
Mitcham, Surrey, UK
The project consisted of the installation of a solar PV system onto the profiled steel sheet roof of a new business park development in Mitcham, South London, and electrical connection into the existing system. The solar photovoltaic (PV) array installed onto the Willow Lane Development is made up of a total of 28 Sanyo 190W PV modules supplied by solarcentury. The array covers a total area of 33m² and is capable of producing a total peak DC power of 5.32 kilowatts under Standard Test Conditions (STC). The estimated annual energy yield for the array is 4,700 kilowatt hours (units of electricity).
As more detailed case study can be found in First Implementation under The Merton Rule
| Date commissioned | 2005.06.22 |
| Technology | Solar PV |
| Installation Type | Pitched roof |
| System size (kWp) | 5.32 |
| Forecast electricity generation / year (kWh) | 4,700.00 |
| Panel area (m2) | 33.00 |
| Building integrated | No |
| CO2 saving / year (kg) | 2,021.00 |
| Type of project | Commercial |
| Attachment | Size |
|---|---|
| Willow_lane_mitcham.pdf | 6.57 KB |